Myth vs. Fact

Setting the Record Straight on the O’Hare Flyer/Great Western Railroad

What it is

Myth: It’s a 15-minute ride.

Fact: Fifteen minutes is the sponsors’ figure for the train itself, terminal to terminal. It does not include getting to the platform at O’Hare, the wait for a train, or getting from the Old Post Office to wherever you are going. By the sponsors’ own schedule — a train every 15 minutes — the average wait is seven and a half minutes and the longest is fifteen. 10 Just miss a train and the train leg alone is 30.

Myth: The O’Hare Flyer is only an express train running from the old Post Office to O’Hare and back again.

Fact: The O’Hare Flyer is a front for the Great Western Railroad. It would take the company 58 years to earn back their investment through the O’Hare Flyer alone.1 The Great Western Railroad will run freight every night from 10 p.m. to 4 a.m. and this is how the company will profit. According to CEO Dave Lundy on September 3, 2026: “Great Western Railroad will be delivering that overnight when the service is not operating.”

Myth: The Great Western Railroad will only carry light freight.

“It’s like three freight cars of flour to a bakery, two freight cars of corn syrup... literally, like you’re talking, hey, you got to deliver three cars of flour, two cars of corn syrup. This is not what I would call heavy freight use,” Lundy said on September 3, 2026.

Fact: The Great Western Railroad will be carrying heavy freight. For flour, each train car holds the equivalent of four semi-trucks. Each train car will weigh at least 200,000 pounds.4

Myth: It just reuses track that’s already there.

Fact: The sponsors said on Oct. 1 they would be “putting in brand new tracks that would run from the downtown all the way up to the airport.” 11 Through River Forest the track would be raised on a 15-foot earth berm topped with a 4½-foot sound wall and an 8-foot fence — 27½ feet from the ground — through residential blocks. 10 Through Thatcher Woods and likely elsewhere, a second track would be added. At O’Hare, a flyover roughly 90 feet high would carry the line over the taxiways to Terminal 2. 12

Who it hits

Myth: The trains will only go through an industrial corridor so no one will be bothered.

Fact: The train speeds through 11 communities past thousands of residences as well as schools, parks, a senior residence, and a hospital. It runs at grade level throughout Forest Park, Melrose Park, River Grove, Franklin Park, and Schiller Park.5

Myth: The trains will not be a danger to the communities.

Fact: The trains will race through five suburban communities at top speed at grade level. Elsewhere in the U.S., such trains have proven deadly. The Brightline train on the coast of Florida “kills someone every 13 days of service, on average,” according to a January 2026 investigation in The Miami Herald.

Myth: All the crossings will be eliminated.

Fact: The sponsors say they will eliminate the crossings in River Forest. North of River Forest, four crossings — 1st Avenue and 5th Avenue in Melrose Park, George Street, and Belmont in Franklin Park — stay at street level unless the Illinois Commerce Commission orders otherwise; the sponsors say they “would like” that and would install gates if it doesn’t happen in time. 10 Federal rules require train horns at street-level crossings. At Chestnut Street the sponsors intend to ask that the crossing be closed. 10

Myth: The O’Hare Flyer is good for all of Chicago.

Fact: No stop is proposed anywhere in Chicago between the Old Post Office and O’Hare. The sponsors say they are “actively considering” one stop, in suburban Forest Park. 11 The eleven communities and the forest preserve along the route get the construction, the crossings and, on parts of the line, overnight freight; they get no station. Fares have not been set. A Chicago Tribune editorial projected $25–$35 a ride; the sponsors have said “about $35,” comparing it to London’s Heathrow Express. The Blue Line is $2.50–$5. 9 11

Health, noise and the environment

Myth: The O’Hare Flyer won’t make any disruptive vibrations.

Fact: No studies have been done to determine whether it’s even possible to create a vibration-free electric train. According to Lundy on September 3, 2026: “Vibration analysis studies have not been done.”

Myth: The O’Hare Flyer will be “whisper quiet.”

Fact: No studies have been done to determine whether it’s even possible to create a quiet train.6

Myth: The O’Hare Flyer won’t harm wildlife in the Forest Preserve.

Fact: No environmental studies have been done to date.7

Myth: It’s been studied.

Fact: No environmental, noise, vibration, traffic or public-health study has been published. On Oct. 1 the sponsors’ representatives said no wildlife, bird, bat, noise or light study had been done for Thatcher Woods and none was yet committed. 11 The ridership study the sponsors cite has not been released. 9

Who pays

Myth: The corporation is using private funding not taxpayer money.

Fact: The corporation intends to apply for Federal funding through the Department of Transportation and will use taxpayer money for their private, for-profit venture.2 Other rail lines, like the Brightline in Florida, have used taxpayer money to pay for safety upgrades that should have been installed from the start.3

Myth: The money is already there.

Fact: The sponsors say one private funding round is closed and a second is under way. They have not said who their investors are, how much they have raised toward a project they put at $2.25 billion, or what return they are promising; asked about the return, they said, “we will not answer that question.” 8 They have also said they expect to refinance with a federal loan once the line is built — which is public credit, not private money. 10

Myth: No public money is involved.

Fact: The sponsors describe the project as private. They have also said they intend to apply for a federal railroad loan; that they plan to grade-separate Madison Street “with IDOT,” the state transportation department; that four crossings in Melrose Park and Franklin Park stay in the street unless the Illinois Commerce Commission orders them separated; and that they expect “an agreement of some type with the city” of Chicago and “some city council process.” 10 12 Every one of those is public money, public land or public approval.

Myth: Private rail costs taxpayers nothing.

Fact: Florida’s Brightline, promoted as “not publicly funded at all,” has taken $486 million in public money, 16 and in 2026 restructured its debt. 17 Its trains have been involved in 196 deaths, most at street-level crossings. 16

Where it stands

Myth: The railroads are on board.

Fact: One of the three railroads, CSX, has signed a letter of intent. Union Pacific and Canadian National have agreed to nothing; the Village of River Forest confirmed this with CN directly. 13 The sponsors said on Oct. 1 that the agreements would be held by Great Western Railroad, a freight company they own, and described CN as “a reasonable possibility.” 11

Myth: It’s a done deal.

Fact: Nothing has been filed. There is no Surface Transportation Board docket, no Illinois Commerce Commission petition, no FAA airport layout plan submission, no environmental review and no agreement with the City of Chicago. By the sponsors’ own account on Oct. 2, the project still needs the FRA, the STB, the FAA, the City’s transportation and aviation departments, a City agreement and “some city council process.” 12 Melrose Park, the Village of River Forest, the West Central Municipal Conference (37 municipalities) and Cook County Commissioner Maggie Trevor are on record against it or calling it premature. 13 14

Myth: There’s no alternative.

Fact: Chicago has two trains to O’Hare now: the Blue Line, 24 hours a day, 40–45 minutes to the Loop, $5; and Metra’s North Central Service. Metra’s draft plan would run trains to O’Hare every 30 minutes, all day, from Union Station, for about $100 million to build. The federal loan program the sponsors are counting on is open to Metra and the CTA today. 15

Sources

Where a sentence names its source, that is the citation. Quotations from Dave Lundy are from the O’Hare Flyer presentation to the High Speed Rail Alliance, September 3, 2026. The Miami Herald figure draws on Federal Railroad Administration data.

  1. Coalition estimate based on the developers’ stated project cost and fare. The developers have not published a payback period. ↩
  2. The O’Hare Flyer presentation to the High Speed Rail Alliance, September 3, 2026. The developers described a U.S. Department of Transportation loan that would replace about three quarters of their private financing once the line is built. They have not named the program. ↩
  3. Miami Herald and WLRN investigation of Brightline, December 2025, and related reporting on publicly funded safety improvements along the Brightline corridor. ↩
  4. Standard North American freight equipment: a loaded covered hopper car has a gross weight of roughly 263,000 to 286,000 pounds, and a single car of flour carries approximately what four semi-trailers carry. ↩
  5. The O’Hare Flyer presentation to the High Speed Rail Alliance, September 3, 2026; residents’ review of the alignment at street level. The street-level crossings are listed on our What We Know page. ↩
  6. The O’Hare Flyer presentation to the High Speed Rail Alliance, September 3, 2026: the developers confirmed no sound study has been done, including for overnight hours. ↩
  7. The O’Hare Flyer presentation to the High Speed Rail Alliance, September 3, 2026: the developers confirmed no environmental impact study has been performed. ↩
  8. The O’Hare Flyer presentation to the High Speed Rail Alliance, September 3, 2026 (question-and-answer session); Eric Zorn, “I, too, have questions about the O’Hare Flyer,” The Picayune Sentinel, September 10, 2026. ↩
  9. Eric Zorn, The Picayune Sentinel, September 10, 2026; Chicago Tribune editorial board; Chicago Transit Authority published fares. ↩
  10. High Speed Rail Alliance webinar with the O’Hare Flyer sponsors, Sept. 3, 2026 (recording). ↩
  11. O’Hare Flyer community meeting, Village of Forest Park, Oct. 1, 2026 (video). ↩
  12. Executives’ Club of Chicago webinar with the sponsors, Oct. 2, 2026. ↩
  13. Village of River Forest, letter to the sponsors and “Questions for the O’Hare Flyer Project Team,” Sept. 28, 2026; Resolution R-26-10, Sept. 14, 2026. ↩
  14. Letters of Melrose Park Mayor Ronald Serpico (Sept. 14, 2026), the West Central Municipal Conference (Sept. 11, 2026) and Cook County Commissioner Maggie Trevor (Sept. 10, 2026). ↩
  15. U.S. DOT Build America Bureau, RRIF program page (transportation.gov/buildamerica/financing/rrif); Metra, Systemwide Network Plan, draft, October 2026, p. 46. ↩
  16. Miami Herald / WLRN, “Private train, public cash,” Nov. 13, 2025. ↩
  17. Associated Press, “Brightline reaches restructuring deal that will give it $490M in new capital, help lower debt,” Sept. 25, 2026. ↩